MULTI-OBJECTIVE PARETO KNEE POINT ANALYSIS
|
||
|
|
Time - Energy - Environment Optimization
|
||
|
|
================================================================================
|
||
|
|
|
||
|
|
================================================================================
|
||
|
|
1. PARETO DATA RANGE
|
||
|
|
================================================================================
|
||
|
|
Completion Time: 101 - 200 years
|
||
|
|
Energy: 15720 - 65177 PJ
|
||
|
|
CO2: 846 - 6393 Mt
|
||
|
|
Elevator Fraction: 54.2% - 100.0%
|
||
|
|
|
||
|
|
================================================================================
|
||
|
|
2. KNEE POINT DETECTION RESULTS
|
||
|
|
================================================================================
|
||
|
|
|
||
|
|
Max Distance (3D):
|
||
|
|
Completion Time: 101 years
|
||
|
|
Energy: 65177 PJ
|
||
|
|
CO2 Emissions: 6393 Mt
|
||
|
|
Elevator Fraction: 54.2%
|
||
|
|
Rocket Sites Used: 10
|
||
|
|
Annual CO2: 63.3 Mt/yr
|
||
|
|
|
||
|
|
Kneedle (Time-CO2):
|
||
|
|
Completion Time: 186 years
|
||
|
|
Energy: 15842 PJ
|
||
|
|
CO2 Emissions: 859 Mt
|
||
|
|
Elevator Fraction: 99.9%
|
||
|
|
Rocket Sites Used: 1
|
||
|
|
Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
Kneedle (Time-Energy):
|
||
|
|
Completion Time: 186 years
|
||
|
|
Energy: 15842 PJ
|
||
|
|
CO2 Emissions: 859 Mt
|
||
|
|
Elevator Fraction: 99.9%
|
||
|
|
Rocket Sites Used: 1
|
||
|
|
Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
Second Derivative:
|
||
|
|
Completion Time: 186 years
|
||
|
|
Energy: 15842 PJ
|
||
|
|
CO2 Emissions: 859 Mt
|
||
|
|
Elevator Fraction: 99.9%
|
||
|
|
Rocket Sites Used: 1
|
||
|
|
Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
Marginal Benefit:
|
||
|
|
Completion Time: 189 years
|
||
|
|
Energy: 15720 PJ
|
||
|
|
CO2 Emissions: 846 Mt
|
||
|
|
Elevator Fraction: 100.0%
|
||
|
|
Rocket Sites Used: 0
|
||
|
|
Annual CO2: 4.5 Mt/yr
|
||
|
|
|
||
|
|
Weighted (Time Priority):
|
||
|
|
Completion Time: 186 years
|
||
|
|
Energy: 15842 PJ
|
||
|
|
CO2 Emissions: 859 Mt
|
||
|
|
Elevator Fraction: 99.9%
|
||
|
|
Rocket Sites Used: 1
|
||
|
|
Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
Consensus (Median):
|
||
|
|
Completion Time: 186 years
|
||
|
|
Energy: 15842 PJ
|
||
|
|
CO2 Emissions: 859 Mt
|
||
|
|
Elevator Fraction: 99.9%
|
||
|
|
Rocket Sites Used: 1
|
||
|
|
Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
================================================================================
|
||
|
|
3. RECOMMENDED SOLUTION
|
||
|
|
================================================================================
|
||
|
|
|
||
|
|
Based on consensus of multiple knee detection methods:
|
||
|
|
|
||
|
|
RECOMMENDED CONFIGURATION:
|
||
|
|
├── Completion Time: 186 years
|
||
|
|
├── Total Energy: 15842 PJ
|
||
|
|
├── Total CO2: 859 Mt
|
||
|
|
├── Elevator Fraction: 99.9%
|
||
|
|
├── Rocket Sites: 1 (low-latitude priority)
|
||
|
|
├── Total Fuel: 80.0 Mt
|
||
|
|
├── Stratospheric H2O: 2.2 Mt
|
||
|
|
└── Annual CO2: 4.6 Mt/yr
|
||
|
|
|
||
|
|
TRADE-OFF ANALYSIS:
|
||
|
|
├── vs Min Time (101yr):
|
||
|
|
│ +85 years,
|
||
|
|
│ -5534 Mt CO2
|
||
|
|
│
|
||
|
|
└── vs Min CO2 (200yr):
|
||
|
|
-14 years,
|
||
|
|
+14 Mt CO2
|
||
|
|
|
||
|
|
|
||
|
|
================================================================================
|
||
|
|
4. INTERPRETATION
|
||
|
|
================================================================================
|
||
|
|
|
||
|
|
The recommended knee point at 186 years represents the optimal
|
||
|
|
trade-off between:
|
||
|
|
|
||
|
|
- TIME: Not the fastest, but 85 years longer gives significant benefits
|
||
|
|
- ENERGY: 15842 PJ (moderate consumption)
|
||
|
|
- ENVIRONMENT: 859 Mt CO2 (substantial reduction from max)
|
||
|
|
|
||
|
|
Key insight: Beyond ~186 years, the marginal environmental
|
||
|
|
benefit of extending timeline decreases significantly. This is the
|
||
|
|
"diminishing returns" point.
|
||
|
|
|
||
|
|
Recommendation: Target 186-year completion with 100%
|
||
|
|
elevator transport and 1 low-latitude rocket sites.
|
||
|
|
|
||
|
|
================================================================================
|